Fully Locally-Funded State Agency/Authority Projects

Fully locally-funded definition: A project for which the funding is derived from the resources of the local Awarding Authority/Owner, including but not limited to federal and local funds, grants and donations (no state bond issue funds such as PSCA are involved).

Fully locally-funded State Agency/Authority projects are administered by DCM's Contract Administration Division, Plan Review Division and Project Inspection Division. State Agency/Authority projects may also be supervised by DCM's Project Management Division when applicable, see assigned agencies.

Form Use and Contract Document Administration Fee

  • Architectural/Engineering Firms:
    • Spec. writers: Flat non-password-protected pdfs of State Agency-owned projects' construction administration documents are available for use in project manuals.
    • Document admin: As part of owners' payments to lead design professionals (LDP) for Service D-Construction Contract Procurement and Service E-Construction Contract Administration, it is the responsibility of the LDP to prepare the construction contract with bond forms, any change order with justification form and supporting documentation, and the certificate of substantial completion with attachments. The LDP is also responsible for preparing other documents such as the final payment checklist with attachments. It is the responsibility of the LDP to ensure attachments from contractors such as bonds' power-of-attorneys, insurance certificates, back-up for change orders, and executed roof warranties are complete and meet the requirements of the Manual of Procedures.
  • The Contract Document Administration Fee-O/A must be paid by the time an Agreement Between Owner and Architect (O/A Agreement) is submitted to DCM for review. The Contract Document Administration Fee-CC and the Permit Fee must be paid by the time a construction contract is submitted to DCM for review. O/A Agreement and construction contract reviews can begin once the appropriate fees have been paid. See User Fees webpage for payment information.
  • Storm damage: If the AL Division of Risk Management (DRM) is the insurer, include the DRM claim #, if any, on O/A Agreements.

Plan Review Submittals and Plan Review Fee

  • The plans and specifications for State Agency projects must be submitted to the DCM Technical Staff for review. DCM's approval of the final submittal must be obtained, as well as DCM's approval of submittals of any Required Actions noted on the Project Comment Letter issued by DCM for the final submittal review must be obtained, prior to the receipt of bids. A plan review can commence upon DCM's receipt of all required items including a completed B-1: Transmittal form; see Manual of Procedures - Chapter 3: Submittal Requirements & Procedures for Plan Review webpage, helpful plan review submittal highlights, and the User Fees webpage. DCM cannot issue a Project Comment Letter unless any required Plan Review Fee has been paid. Storm damage: If the AL Division of Risk Management (DRM) is the insurer, include the DRM claim #, if any, on B-1 transmittals.

Pre-Construction Conference, Inspections and Permit Fee

  • All State Agency projects require a DCM Inspector-facilitated pre-construction conference which can be scheduled after the Permit Fee is paid; see User Fees webpage for payment information. The Permit Fee and CDA Fee-CC must be paid by the time a construction contract is submitted to DCM for review. A pre-construction conference can occur once the Inspector receives a copy of the fully executed construction contract and notice to proceed from DCM's office. Benchmarks must then be met for required inspections as listed in the Pre-Construction Conference Checklist. For more details, see DCM's Manual of Procedures.

Special Circumstances

Public School and College Authority (PSCA)

  • When a State Agency project is partially or fully PSCA-funded, PSCA forms must be used during the project (instead of state agency standard forms) and submitted to DCM; see DCM's PSCA webpage for guidance.

Forms: Paperless with Electronic Signatures, for Fully Locally-Funded State Agency/Authority Projects

Links which are only for the use of the Lead Design Professional Firm to activate the paperless process:
State Agencies subject to Contract Review Permanent Legislative Oversight Committee:
Agreement Between Owner and Architect (Contract Review Report, Governor's Additional Questions, Immigration Statement, DCM Forms B-2, B-2A, B-1A, & B-3A, Beason-Hammond Certificate, Contract Review Manual)
State Agencies and Authorities NOT subject to Contract Review Permanent Legislative Oversight Committee:
Agreement Between Owner and Architect (DCM Forms B-2, B-2A, B-1A, B-3A)
State Agencies subject to Contract Review Permanent Legislative Oversight Committee:
Cost and/or Change-of-Time Amendment (Contract Review Report, Governor's Additional Questions, Immigration Statement, DCM Forms B-4, B-1A & B-4A, Contract Review Manual)
State Agencies subject to Contract Review Permanent Legislative Oversight Committee:
No Cost Amendment (DCM Forms B-4, B-4A; does not go to CRPLOC)
State Agencies and Authorities NOT subject to Contract Review Permanent Legislative Oversight Committee:
Amendment (DCM Forms B-4, B-4A.)
Lead Design Professional's Invoice (attachment of DCM Form B-5A, or LDP's invoice form provided it includes all requested information and statements of DCM Form B-5A)
Construction Contract for projects with a contract sum of $100,000.00 or more (DCM Forms C-5, C-6, C-7, C-8, B-1A, B-7A; includes required Payment & Performance Bonds)
Construction Contract for projects with a contract sum of less than $100,000.00 (DCM Forms C-5, C-8, B-1A, B-7A; without Payment & Performance Bonds)
Change Order for contracts with an original sum of $100,000.00 or greater, and with a Change Order Additive Cumulative Amount (this change order amount plus any previous change order amounts) Exceeding 10% of original Contract Sum; shall be routed to the Contractor's Surety and to the Owner's Legal Counsel. May be used for all Change Order amounts, and may include a change-of-days. (DCM Forms C-12, B-11).

Link which is only for the Construction Contractor Company to activate the paperless process:
Contractor's Payment Application (DCM Form C-10, attachment of DCM Form C-10SOV, and attachment(s) when required of DCM Forms C-10SM, C-11, C-9, C-13, C-14, C-18, C-19, C-20)

Link which may be activated by the Lead Design Professional Firm or the Construction Contractor Company:
Certificate of Substantial Completion (DCM Form C-13; initiate the Certificate PowerForm after Substantial Completion is declared Accepted at a Final Inspection meeting and you have received the DCM Inspector's Final Inspection report. Do not initiate the Certificate PowerForm prior to those two events.)

Forms: Pdfs and Excel Documents, for Reference and for use as Attachments transmitted via above DocuSign links

Forms

Brief Instructions for Lead Design Professional Firms


Owner/Architect/Engineer Documents

(For more detailed instructions, see DCM's Manual of Procedures)

Include 1 copy with each plan review submittal.
Fee due before O/A Agreement is reviewed by DCM.
For reference.
Give Article 13 to Designer's insurance rep.
Include 1 completed hardcopy with the AL Vendor Disclosure Statement.
Deliver 1 original notary sealed hardcopy with Form B-1A to DCM office.
Attach 1 copy of Designer's entire MOU to Agreement in DocuSign.
Owner required to apply for a certificate on each project.
Attach a completed copy to each Amendment in DocuSign.
Transmit Statement via DocuSign.

Construction Administration Documents


For reference.
C-1A: Sample Invitation to Bid - updated Feb 2024
For use as needed.
C-2: Instructions to Bidders - updated Feb 2024
For reference.
Attach 1 copy to Contract in DocuSign.
Attach 1 copy to Contract in DocuSign.
C-4: Bid Bond - updated Feb 2024 (removed staple ref)
May be used in lieu of a cashier’s check.
Attach one copy to Contract in DocuSign, notary seal must show.
Fee due before Contract is reviewed by DCM.
Fee due before Contract is reviewed by DCM, & before scheduling pre-con.
For reference.
Give Article 37 to contractor's insurance rep.
Include 1 completed hardcopy with the AL Vendor Disclosure Statement.
Deliver 1 original notary sealed hardcopy with Form B-1A to DCM office.
Attach 1 copy of contractor's entire MOU to Contract in DocuSign.
Contractor required to apply for a certificate on each project.
Required on projects with a $100,000 contract or more.
For reference.
For use as needed.
For use as a draft; initiate actual pay app via DocuSign.
Transmit via DocuSign.
Transmit via DocuSign.
Transmit via DocuSign; contractor may use own form.
C-9: General Contractor's Roofing Guarantee - updated Feb 2024 (removed staple ref)
Transmit via DocuSign with Substantial Completion Cert. & final pay app.
Transmit via DocuSign with final pay app.
Transmit via DocuSign with final pay app.
Transmit via DocuSign with final pay app.
If required by Owner, transmit via DocuSign with final pay app.
Transmit via DocuSign with final pay app.