- Plans and specifications of all K-12 projects must be submitted to the DCM Technical Staff for review, regardless of estimated construction cost.
- K-12 projects estimated over $750,000.00:
A plan review can commence upon DCM's receipt of all required items including a completed
B-1: Transmittal form; see Manual of Procedures -
Chapter 3: Submittal Requirements & Procedures for Plan Review, helpful plan review submittal highlights,
and the User Fees webpage. DCM cannot issue a Project Comment Letter unless any required Plan Review Fee has been paid. DCM's approval of the final submittal must be obtained, as well as DCM's approval of submittals of any Required Actions noted
on the Project Comment Letter issued by DCM for the final submittal review must be obtained, prior to the receipt of bids. Project Comment Letters issued by DCM Plan Reviewers are
emailed to the Owner, Lead Design Professional, and State Fire Marshal's Office.
- K-12 projects for capital improvement, or alterations, additions, repair, or maintenance of heating, ventilation, and air conditioning systems or any alterations, additions, repair, or
maintenance of a roof, with both both a certified estimate after design completion of $750,000.00 or Less:
- Determination of whether or not a project is in the $750,000.00 or Less classification is based on the total estimated cost of the entire project including all phases and bid packages.
- $750,000.00 or Less projects do not owe Plan Review Fees; such projects are still subject to DCM plan reviews which can commence upon DCM's
receipt of all required items including a completed B-1: Transmittal form;
see Manual of Procedures - Chapter 3: Submittal Requirements & Procedures for Plan Review, and helpful
plan review submittal highlights.
- DCM's Project Comment Letter for the Final submittal must be obtained, prior to the receipt of bids. Project Comment Letters issued by DCM Plan Reviewers are emailed to the Owner,
Lead Design Professional, and State Fire Marshal's Office.
If the project involves a storm shelter, see DCM Bulletin #23-01 Updated Guidance
on Mandatory Storm Shelters in Public and Private K-12 Schools required by the International Building Code dated 11/21/22, and note that the following three documents must be included in the
project manual submitted for final plan review: DCM Form B-15: Owner’s Statement of Responsibility for
Tornado Storm Shelter (Hurricane Shelter Where Applicable), DCM Form C-17: Contractor’s Statement of Responsibility for Construction
of Tornado Storm Shelter (Hurricane Shelter Where Applicable), and DCM Form B-14: Certification of Structural
Observations.
Private K-12 school projects use contract documents as deemed appropriate by the Owner.
Special Circumstances
Schoolhouses are within DCM's Code Jurisdiction; Definition per Alabama Administrative Code 355-12-1.04
"Schoolhouses: Any building or other structure erected or acquired by the public schools of Alabama and also shall mean any private building in which 25 or more persons are congregated
regularly for the purpose of instruction in any branch of knowledge."